Log in

Register

Please choose the option that matches your business

That looks like a track and trace number, do you want to track on this number?

How do you want to track your shipment?

Find exactly what you are looking for

Select your location and language

DSV and Schenker have joined forces

dbschenker.com has been merged into DSV.com. Go to your DB Schenker self-services or close this message to visit DSV.com. 

PLEASE UPDATE YOUR FAVOURITES / BOOKMARKS.

Schenker self-service tools Read more about the Schenker acquisition
DSV's projects team walking alongside transformer transport going to Iraq

DSV completes 600km inland transport of transformers across Iraq

A complex cross-country logistics operation highlights DSV's expertise in oversized cargo transport for critical energy infrastructure in challenging environments

DSV has successfully completed the transport and installation of three transformers with a combined weight of approximately 70 tonnes for a customer in the Energy sector in Iraq, reinforcing its expertise in project logistics for large-scale energy infrastructure across high-complexity inland routes.

The transformers were moved as breakbulk cargo from DSV's yard in Basra in southern Iraq to the Al-Khalidia sub-station site in Ramadi - Al-Habbaniyah, located in the western region of the country. The operation covered approximately 600 kilometres and was completed within two days, in line with the agreed project schedule.

The movement of three transformers through Iraq's inland corridor required detailed engineering, specialist heavy transport equipment, and close coordination with local authorities across multiple jurisdictions.

Transport was executed using multi-axle hydraulic trailers, enabling safe load distribution and controlled movement of the cargo across variable and at times deteriorated road conditions.

Key operational challenges included:

Despite these challenges, all three transformers were delivered safely and on time.

DSV managed the full logistics scope, including planning, loading, inland transport, delivery, and installation.

Installation was executed by using jacking and pulling method. This ensured full control over safety, sequencing, and installation quality during final positioning at site.

The integrated scope included:

"Projects like this highlight the importance of combining global project logistics expertise with strong local operational knowledge. Every stage, from route planning to final installation, requires precision, coordination, and the ability to adapt to real-world conditions on the ground."

Joe Waked, General manager, Operations, Iraq - DSV

The delivery supports ongoing investment in power generation and grid expansion across Iraq, where reliable transport of oversized equipment is essential to infrastructure development and energy stability.

As demand for energy infrastructure continues to grow across the Middle East, DSV's project logistics capabilities enable customers to move critical equipment safely, efficiently, and on schedule, even in highly complex inland environments.